6.4.4
Testing of the pipe Line
6.4.4.1 GENERAL
After laying and jointing the pipe line be pressure
tested to ensure that pipe joints are sound enough
to withstand the maximum pressure likely to be developed
working conditions.
6.4.4.2 TESTING OF PRESSURE PIPES
The field test pressure to be imposed should be
not less than the greatest of the following.
(a) 1 1/2 times the maximum sustain operting pressure
(b) 1 1/2 times the maximum pipe linstatic pressure
(c) Sum of the maximum sustained operating pressure
and the maximum surge pressure.
(d) Sum of the maximum pipe line static pressure
and the maximum surge pessure, subject to a maximum
equal to the works test pressure for any fittings
incorporated.
The field test pressure should whereever possible
be not less than 2/3rd work test pressure appropriate
to the class of pipe except in the case of spun
iron pipes and should be applied and maintained
for atleast four hours. If the visual inspection
satisfies that there is no leakage the test can
be passed.
Where the fields test pressure is less than 2/3
the works test pressure, the period of test should
be increased to atleast 24 hours. The test 1kg/cm2/min.
If the pressure measurement are not made at the
lowest point of the section an allowance should
be made for the difference in static head between
the lowest point and the point of measurement to
ensure that the maximum pressure is not exceeded
at the lowest point. If a drop in pressure is not
exceeded at the lowest point. If a drop in pressure
occurs the quantity of water added in order to re-establish
the test pressure should be carefully measured.
This should not exceed 0.1 liter per mm of pipe
diameter per KM of pipe line per day for each 30
meter head of pressure applied.
In case of gravity pipes maximum working pressure
shall be 2/3 works test pressure.
The hydrostatic test pressure at works and at field
after installation and the working pressure for
the difference classes of C.I Pipes are given in
Appendix 6.4.
The allowable leakage during the maintenance stage
of pipes carefully laid and well tested during construction,
however should not exceed.
qL=ND \/P
-------
115 (6.11)
where,
qL = Allowable leakage in cm3/ hour
N = No of joints in the length of pipe line
D = Diameter in mm
P = the average test pressure during the leakage
test in kg/cm2.
Where any test of pipe laid indicates leakage greater
than the specified as per the above formula, the
defective pipe (s) or joint(s) shall be repaired/
replaced until the leakage is with in the specified
allowance.
The above is applicable to spigot and socket Cast
Iron pipes and A.C pressure pipes whereas twice
this figure may be taken for steel and prestressed
concrete pipes.
6.4.4.3 TESTING OF NON-PRESSURE CONDUITS
In case of testing of non pressure conduits the
pipe line shall be subject to a test for of 2.5
meters head of water at the height point of the
section under test for 10 minutes. The leakage or
quantity of water to be supplied to maintain the
test pressure during the period of 10 minutes shall
not exceed 0.2 liters/ mm dia of pipes per kilometer
length per day.