6.7.3
Pipe Joints
There are two types of joints forAC pipes.
-Cast iron detachable joint, and
- AC coupling joint.
(a) Cast iron detachable Joints
This consists of two cast iron flanges, a cast iron
central collar and two rubber rings along with a
set of nuts and bolts, for a particular joint. For
this joint of the AC pipes should have flush ends.
For jointing a flange, a rubber ring and a collar
are slipped to the first pipe in that order; a flange
and a rubber ring being introduced from the jointing
of the next pipe. Both the pipes are now aligned
and the collar centralised and the joints of the
flanges tightened with nuts and bolts.
(b) A.C Coupling Joint
This consists of an A.C Coupling and three special
rubber rings. The pipes for these joints have chamfered
ends. These rubber rings are positioned in the grooves
inside the coupling, then grease is applied on the
chamferred end and the pipe and coupling is pushed
with the help of a jack against the pipe. The mouth
of the pipe is then placed in the mouth of the coupling
end and then pushed so as to bring the two chamfered
ends close to each other. Wherever necessary change
over from cast iron pipe to AC pipes or vice versa
should be done with the help of suitable adapters
IS 6530- 1972 may be followed for laying A.C pipes.
6.7.4 Pressure Testing
The procedure for the test as adopted generally
is as follows
(a) At a time one section of the pipe line between
two sluice valves is taken up for testing. The section
usually taken is about 500 meters long.
(b) One of the valves is closed and the water is
admitted into the pipe through the other, manipulating
air valves suitably.
(If there are no sluice valves in between the section,
the end of the section can be sealed temporarily
with an end cap having an outlet which can serve
as an air relief vent or for filling the line as
may be required. The pipe line after it is filled,
should be allowed to stand for 24 hours before pressure
testing).
(c) After filling this sluice valve is closed and
the pipe section is isolated.
(d) Pressure gaugages are fitted at suitable intervals
on the crown into the holes meant for the purpose.
(e) The pipe section is then connected to the delivery
side of the pump through a small valve.
(f) The pump is then worked till the pressure inside
reaches the designed value which can be read from
the pressure gauges fixed.
(g) After the required pressure has been attained,
the valves is closed and the pump disconnected.
(h) The pipe is then kept under the desired pressure
during inspection for any defect i.e. leakages at
the jionts etc. The test pressures will be generally
as specified in 6.7.1 and Appendix 6.4. The water
will then be emptied through scour valves and defects
observed in the test will be rectified.